North End Shipyard Visitor Centre, Hull
CJ Joinery Contracts worked with Ashcourt Group on the new North End Shipyard Visitor Centre in Hull, delivering a technically demanding joinery and drylining package as part of the wider Hull Maritime regeneration programme.
Project overview
The North End Shipyard Visitor Centre was developed by Hull City Council as part of the wider Hull Maritime programme and provides a permanent visitor and learning facility alongside the restored Arctic Corsair, Hull's last surviving sidewinder trawler.
The building was designed by Purcell to the Passivhaus standard, combining a flood-resilient concrete ground floor with an insulated timber-frame upper structure.
For CJ Joinery, the project was particularly significant because it was the team's first Passivhaus project. The strict requirements around insulation, airtightness, membranes and construction interfaces created a steep learning curve, but the team adapted quickly and successfully delivered the package.
Key figures
- £365k
- CJ Joinery package
- Approx. £7.5m
- Wider North End Shipyard Visitor Centre & Dry Dock works
- 0.47 ACH @ 50 Pa
- Achieved airtightness
- 1,232m²
- 400mm roof wood-fibre insulation
- 846m²
- 300mm wall wood-fibre insulation
- Approx. 21
- Internal doorsets
- 14
- Timber side panels installed
- 2
- Gable ends installed
- UK first
- Passivhaus-certified museum
Scope of works
CJ Joinery delivered a mixed package of supply-and-install works together with labour-only installation of the principal timber structure, insulation and timber framing.
- Labour-only installation of the principal timber-frame structure
- Installation of sole plates, 14 timber side panels and 2 gable ends
- Installation of the timber roof structure, roof noggins, splice plates and structural plywood
- 1,232m² of 400mm wood-fibre roof insulation
- 846m² of 300mm wood-fibre wall insulation
- 50mm wood-fibre sarking boards
- PIR insulation to timber rafters and wall studs
- Vapour-control layers, membranes, tapes and associated airtightness detailing
- I-joist first-floor and loft construction
- Drylining, plasterboarding, suspended and acoustic ceilings, dot-and-dab wall linings, plastering and skimming
- Engineered timber flooring
- Supply and installation of approximately 21 internal doorsets and ironmongery
- Skirtings, window boards and numerous additional works and variations
The challenge
The biggest challenge was delivering CJ Joinery's first project to the demanding Passivhaus standard. The building envelope relied on extremely high levels of insulation and airtightness, meaning the quality of every junction, membrane, fixing and interface was critical.
CJ Joinery's team had to quickly develop a strong understanding of Passivhaus construction while maintaining the required quality and programme.
Our approach
The team worked closely with Ashcourt and the wider design team to understand the specialist details and adapt working methods as the project progressed.
- Correct installation of thick wood-fibre insulation build-ups
- Continuity of vapour-control and airtightness membranes
- Careful detailing around timber-frame junctions
- Minimising uncontrolled penetrations through the airtight layer
- Responding quickly to design changes and additional works
- Supporting the project team during airtightness testing
Although Passivhaus construction was new to CJ Joinery, the site team rose to the challenge and became increasingly experienced in the specialist requirements as the project progressed.
Airtightness performance
The completed building achieved an airtightness result of 0.47 air changes per hour at 50 Pa, comfortably inside the Passivhaus requirement of no more than 0.6 ACH @ 50 Pa.
CJ Joinery understands the result to be among the strongest achieved on a commercial Passivhaus project in the UK. The result was particularly significant given this was CJ Joinery's first Passivhaus project.
Outcome
CJ Joinery successfully completed its package and made a major contribution to achieving the building's required airtightness and thermal-performance standards.
The project achieved full Passivhaus certification in 2025 and became the UK's first Passivhaus-certified museum.
For CJ Joinery, North End Shipyard demonstrated that an experienced commercial joinery team could successfully adapt to a highly technical low-energy construction standard, solve unfamiliar detailing challenges and deliver the required performance.
Frequently asked questions
On-site imagery
More projects like this
Rutland Mills / Tileyard North, Wakefield
Structural timber and joinery across four Grade II listed mills at Tileyard North.
Read case studyRetailBoyleSports Nationwide Retail Rollout
Nationwide retail joinery rollout across 28+ high-street locations.
Read case studyAutomotiveJaguar Land Rover Design and Engineering Centre
Labour-only Cat B joinery installation for the £200m JLR Design & Engineering Centre.
Read case study