Case Study / Fire Doors

Redtape Studios, Sheffield

Managing a varied fire-door package across a large multi-level refurbishment

Sheffield
Fire Doors

Project overview

Redtape Studios was upgraded as part of Sheffield City Council refurbishment works, with fire doors and screens forming a key part of the compliance package.

CJ's role focused on supplying and installing the required fire-door assemblies and screens and providing BM TRADA sign-off.

Key figures

£75k
CJ Joinery package
£600k
Wider project value
Multi-level
Large existing building
Mixed door types
Varied installation package
BM TRADA
Fire-door sign-off
Sheffield City Council
Client
Scope of Works

Scope of works

  • Supply and installation of fire doors
  • Supply and installation of associated frames and screens
  • Installation of ironmongery and fire-door components
  • BM TRADA-compliant installation records
  • BM TRADA sign-off
  • Coordination across multiple floors and work areas
  • Snagging and close-out of the fire-door package
The Challenge

The challenge

The biggest task was managing a varied mix of doors across a large multi-level existing building.

Some areas remained live while others were handed over, so CJ had to adapt its sequencing while maintaining consistent installation standards and compliance evidence across different door types and locations.

Our Approach

Our approach

CJ broke the work into manageable floor and door-type sequences and maintained clear installation records as the works progressed.

This allowed the team to control quality across the mixed door schedule, work around live areas when necessary and close out the BM TRADA requirements efficiently.

Outcome

CJ successfully completed the fire-door and screen package and achieved the required BM TRADA sign-off.

The project demonstrates CJ Joinery Contracts' ability to manage complex, high-volume fire-door works across existing multi-storey buildings with mixed access conditions.